Lift design

Trinity plans to install a lift in the building during 2027.  The following design outline is subject to change!​​​​​​​ 

Lower level plan
Upper level plan
Upper level plan

Relocation of the Gentlemen's and Ladies toilets will allow these facilities to be updated, a much needed improvement, but it is planned to relocate and retain the Edwardian basins. 

​

The new doors will match the existing style of the building.  

​

Finally the work will involve replastering and making good.

​

At the lower level the lift door will be to the right as you enter the side door by the kitchen.

​

The lift shaft (highlighted in yellow) will occupy some of the space currently used by the Gentlemen's toilets, the remainder being used to provide a small storeroom. 

​

New Gentlemen's toilets will be installed using part of the space currently occupied by the Terrace Store room (highlighted in blue).

​

The remainder of the Terrace Store room will remain as storage, accessed from the Terrace Room.  

At the upper level the lift door will be opposite a new door from the Parlour.

​​

The lift shaft (highlighted in yellow) will occupy some of the space currently used by the Ladies' toilet, the remainder being used to provide a small unisex toilet adjacent to the Parlour.

​

 

At the intermediate level the lift door will be between the stairs landing and the corridor to the church.

​​

The lift shaft (highlighted in yellow) will occupy some of the space currently used by the Ladies' toilets on the floor above, the remainder being used to provide a small unisex toilet opposite the corridor to the church.